The scheduled start date of this task plus its duration makes it complete after its end constraint date.
To resolve this, do one of the following:
- change the scheduling for this task to As Early As Possible, which will allow it to be scheduled before the end constraint of %1@,
- move the end constraint back to match the scheduled date of %2@, or
- remove the end constraint entirely.